Work on the new space is progressing nicely and we now have some tentative time frames for upcoming milestones.  ALL SUBJECT TO CHANGE of course, but should be close to the time frames below and we will keep you posted!

May 5

  • Start work on new drainage pond, drainage lines through parking lot and parking lot expansion

June 1

  • New Ministry Hub ready to use!
  • Last service in existing sanctuary before work starts in there

June 8- July 6        

  • Sunday services to be held outside.  If weather is bad, we will set up chairs in the Ministry Hub and hold services there.
  • Install new glass doors to sanctuary, move sound booth
  • Install most of landscaping, parking lot complete

July 13

  • Sunday services move back to remodeled sanctuary

Aug 1

  • Celebration dinner at Chaska Event Center!  

Aug 3

  • Sunday service devoted to dedication of new Ministry Hub and 25 year anniversary. 


As always, if you have any questions, feel free to contact Casey Campbell, Waterbrooke's construction liaison.